(2007-04-07) During the first quarter, the company witnesses a peak after a peak in
shiprepair, newbuilding, and steel construction. The company has accomplished
25.47% of the production value plan of year 2007, with 22.93% increasing
as against last year;The production value of shiprepair achieved 29.38%
of the yearly plan, with 63.22% increasing as against last year. Total
31 vessels delivered including 3 vessels of conversion. And also, two
more 53000DWT newbuilding contracts has been signed. The newbuilding division
realized the target of "4 vessels under construction, 2 vessels assembling
on the slipway, 2 vessels launching, and one delivery". The production
value of newbuilding increased 5.24% as against last year. Steel construction
has scored up good result as well.
|
||
|